CPI website: 168-hour Full Load Operation of the first unit in Atlas Project

    At 14:00 on August 23, the NO.2 unit of Turkey’s Atlas Project (600MW power plant) (the first power generator), constructed by the parent engineering company, passed full load operation successfully.

    During the 168-hour pilot run, all the economic and technical indicators reached or exceeded the design values, with automatic input rate reaching 100%, operational rate of protection system reaching 100% and the main instrument input rate 100%. And the desulfurization synchronization input, high plus investment, investment ESP, machines, stoves and electricity all reached full nameplate output.